answer to Q 20 is $7470.022. how to do it: watch this video: http://www.youtube.com/watch?v=zGRVVSC4UUQ
ReplyDeleteanswer to Q 33 is correct. (answer 4)
Configuration Management system deals with Processes and procedures.
Change Management system focuses on identifying, documenting and controlling changes to project and product baselines. (refer PMBOK page94)